Installing a photovoltaic system

  1. The first step is to commission a licensed electrical installation company, which will submit a technical connection request (TAG) and an installation notice to SME and will register your system in the Pronovo customer portal.
  2. Once the installation notice has been approved, the installation company will install your PV system.
  3. The installer submits the meter installation to SME before commissioning, and a meter installer adapts the measurement infrastructure on-site. The initial commissioning must be done in the presence of a representative of St. Moritz Energie.
  4. The installation company commissions an accredited auditor with certification of the system. The installer of your PV system will issue a safety certificate for you and submit a copy with SME. The certification must be submitted to Pronovo within one month of commissioning.

Sale of electricity